August 20th, 2026 Local News
(Farmington, MO) Members of the St. Francois County Commission are approving a change order for the Wolf Creek Bridge project. The Presiding Commissioner of St. Francois County, Harold Gallaher, says it involves two box culverts that were to be placed in the road on the western approach to the bridge.
According to Gallaher the work will now involve a concrete base slab to make the land structurally sound for the culverts. THe Wolf Creek Bridge work could be completed by the 2nd week of September.